Placer County Unincorporated, California · General provision
Section 17.56.280
Extracted standards
3 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Allowed zones for temporary dwelling during construction
residential-agricultural (RA), farm (F), resort (RES), residential-forest (RF), or agricultural/exclusive (AE) zone districts
- Maximum duration2 years
A temporary dwelling shall be allowed for a maximum of two years unless an extension is obtained.
- Security deposit for mobile homeManufactured homeA dwelling built in a factory to a federal standard and transported to the site.250 dollars
Before issuance of a building permit for a temporary mobile home, the applicant shall deposit a letter of credit or cash in the amount of $250.
From the ordinance
The use of a temporary dwelling during the construction of a permanent dwelling shall be allowed only in the residential-agricultural (RA), farm (F), resort (RES), residential-forest (RF), or agricultural/exclusive (AE) zone districts. A temporary dwelling shall be allowed for a maximum of two years unless an extension is obtained.