Appomattox County Unincorporated, Virginia · General provision

19.6-76.3.1(A)(2)

Dimensional standards

Servicing

Geographic extent
Areas shown on FIRM as AE or AH zones

Extracted standards

1 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Floodplain

  • No development causing >1 foot increase

    no new construction, substantial improvements, or other development (including fill) shall be permitted within the areas of special flood hazard, designated as Zones A1-30, AE, or AH on the FIRM, unless it is demonstrated that the cumulative effect... will not increase the water surface elevation of the base flood more than one foot

From the ordinance

no new construction, substantial improvements, or other development (including fill) shall be permitted within the areas of special flood hazard, designated as Zones A1-30, AE, or AH on the FIRM, unless it is demonstrated that the cumulative effect... will not increase the water surface elevation of the base flood more than one foot
19.6-76.3.1(A)(2)