Portsmouth, Virginia · General provision

Sec. 40.2-217(J)(6)(c)

Extracted standards

3 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Adjacent site requires permit

    If construction-related activities occur on adjacent site, a Temporary Use Permit is required. Such uses shall be removed within 30 days after CO and site restored.

  • Removal within 30 days after CO30 days

    Such uses shall be removed within 30 days after issuance of a Certificate of Occupancy.

  • Same site no permit required

    Temporary construction-related activities may occur on the same site as construction activity without obtaining a Temporary Use Permit.

From the ordinance

Temporary construction-related activities for new construction, including construction offices, storage buildings, outdoor storage, and employee parking areas, may occur on the same site as construction activity without obtaining a Temporary Use Permit. Such uses shall be removed within 30 days after issuance of a Certificate of Occupancy.
Sec. 40.2-217(J)(6)(c)