Extracted standards
5 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Annual environmental audit
Annual environmental audit by qualified independent contractor.
Master plan of proposed development and use shall be submitted.
- Min parcel for industrial/construction debris871,200 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
Minimum parcel size for industrial or construction debris landfill = 20 acres.
- Min parcel for sanitary landfill4,356,000 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
Minimum parcel size for sanitary landfill = 100 acres.
- Type D buffer required
A Type D buffer yard shall be provided.
From the ordinance
Landfill: min parcel 20 acres industrial, 100 acres sanitary, Type D buffer, master plan, annual audit.