Extracted standards
1 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Temporary trailer coach occupancy during construction6 months
Owner may occupy a trailer coach during construction for up to 6 months with permit, renewable once for an additional 6 months.
From the ordinance
During the construction of a building or buildings, the owner of the lot may, for his own occupancy, apply to the building inspector for a permit to occupy a trailer coach for a period not to exceed six months.