  • Appeal of conditions of approval

    The conditions of approval may be appealed as provided in Chapter 20.208 (Appeals), Section 20.208.015.

  • Environmental review required for significant impacts

    If, after review of the Environmental Review Checklist, it is determined that the development project may have a significant adverse environmental impact then the applicant shall be subject to Section 20.188.025.

  • Industrial development review required

    Projects subject to development review shall be those projects, located in an industrial zone and identified in Appendix A or B.

  • No work before approval

    No work shall be commenced nor any building occupied, until the industrial development project has received approval pursuant to this Chapter, except as specified in Section 20.188.060.

  • At the discretion of the Zoning Administrator, permits may be authorized for preliminary grading and excavating; or foundation work.

From the ordinance

Projects subject to development review shall be those projects, located in an industrial zone and identified in Appendix A which are found to require further review due to the specific nature of the proposed activity; or identified in Appendix B which require mitigation of negative environmental impacts identified in the Environmental Checklist.