Dimensional standards
Servicing
- Geographic extent
- Citywide
Extracted standards
11 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Appeal deadline30 days
Any permit applicant ... may request in writing a formal hearing ... provided a petition requesting such hearing is filed with the administrator within 30 days after notice of such action is given.
- Completeness determination time15 days
The administrator shall determine the completeness of a plan ... within 15 calendar days of receipt.
- Exemption for other activities disturbing less than 1 acreacre43,560 square feet — about the size of an American football field without the end zones. unless part of larger common plan1 acresacre43,560 square feet — about the size of an American football field without the end zones.
Land-disturbing activities that disturb less than one acre of land area are exempt unless these activities are part of a larger common plan of development or sale that is one acre or greater of disturbance.
- Exemption for single-familySingle-family dwellingOne dwelling unit on its own lot, usually detached from its neighbours. residences disturbing less than 1 acreacre43,560 square feet — about the size of an American football field without the end zones.1 acresacre43,560 square feet — about the size of an American football field without the end zones.
Single-family residences separately built and disturbing less than one acre and not part of a larger common plan of development or sale, including additions or modifications to existing single-family detached residential structures.
- Post-construction inspection frequency5 years
Post-construction inspections of stormwater management facilities ... shall occur, at minimum, at least once every five years.
- Maximum permit extension without reevaluation5 years
No land development permit or other land-disturbing activity shall be granted or extended for more than a total five consecutive years from the date of the original permit issuance without reevaluation of the stormwater management requirements.
- Permit required for land-disturbing activities of 1 acreacre43,560 square feet — about the size of an American football field without the end zones. or more1 acresacre43,560 square feet — about the size of an American football field without the end zones.
Except as provided herein, no person may engage in any land-disturbing activity until a VSMP authority permit has been issued... (d) Exemptions: ... (3) Single-family residences separately built and disturbing less than one acre... (4) Land-disturbing activities that disturb less than one acre of land area are exempt unless these activities are part of a larger common plan of development or sale that is one acre or greater of disturbance.
- Plan review time60 days
The administrator shall have an additional 60 calendar days from the date of the communication of completeness to review the plan.
- Plan validity period before reevaluation180 days
Should a land-disturbing activity associated with an approved plan ... not begin during the 180-day period following approval or cease for more than 180 days, the city may evaluate the existing approved stormwater management plan...
- Record retention period5 years
Parties responsible for the operation and maintenance of a stormwater management facility shall make records ... and shall retain the records for at least five years.
- Review time for resubmitted plans45 days
The administrator shall review any plan that has been previously disapproved, within 45 calendar days of the date of resubmission.
From the ordinance
No person may engage in any land-disturbing activity until a VSMP authority permit has been issued... Exemptions for single-family residences disturbing less than one acre.