Henrico County Unincorporated, Virginia · General provision

Sec. 24-2314 through 24-2320

Extracted standards

6 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Fire hydrant requirement

    The construction plan must show, and the developer must provide, fire hydrants as required by the Statewide Fire Prevention Code and the Department of Public Utilities standards.

  • Improvement installation deadline24 months

    All improvements must be installed within 24 months of construction plan approval unless the Planning Director approves a longer period due to the size or complexity of the project.

  • Notice for street/storm sewer work24 hours

    The owner must notify the County Engineer at least 24 hours prior to beginning any work on streets or storm sewers.

  • Notice for water/sewer work48 hours

    The owner must notify the Department of Public Utilities at least 48 hours prior to beginning any work on County water or sewer construction.

  • The Planning Director is authorized to approve administrative modifications to the standards in Table 2319: Allowed Administrative Modifications, up to the amounts specified in Table 2319.

  • Construction of or alterations to one single-family dwelling is exempt from site plan requirements.

From the ordinance

Procedural requirements for plan of development, site plan, variance, interpretation, proffer interpretation, administrative modification, and appeal.
Sec. 24-2314 through 24-2320